The applicant’s engineer shall submit a letter to the city certifying that the completed project conforms to the conditions of the permit and approved plans and all grading work, drainage facilities, erosion control measures, etc., have been completed in accordance with the issued permit. The report shall be stamped and signed by the engineer and shall be worded as follows:

“I have inspected the project and find that the work substantially conforms to the terms and conditions of the permit and the intended design for the project.”

Minor alterations to the system must be listed in the approval letter or noted on reproducible as-built drawings which must be submitted with the approval letter. (Ord. 1113-15 § 8; Ord. 810 § 1, 1996).